The Constitutional Financing Fund for the Northeast (FNE), operated by Banco do Nordeste (BNB), is the main source of long-term credit for projects in the area covered by Sudene, the Northeast development agency. We advise companies, concessionaires and SPVs from eligibility through to signing.
- 2026 budget
- BRL 52.6 billion, of which BRL 6.3 billion under FNE Proinfra
- Tenor
- Up to 12 years for general investment and up to 34 years for infrastructure
- Grace period
- Up to 4 years for general investment and up to 8 years for infrastructure
- Interest
- From IPCA + 3.78% to IPCA + 9.78% per year for investment
- Participation
- From 50% to 100% of the investment, depending on size and location
- Coverage
- 2,074 municipalities: the Northeast and part of Minas Gerais and Espírito Santo
Rates
Reference rate in November 2026
- Investment — medium-sized and large companies
- IPCA + 3.78% to 9.78% per year
- Water, sewage and logistics infrastructure
- IPCA + 3.02% to 4.35% per year
- Other infrastructure
- IPCA + 5.67% to 8.15% per year
- Science, technology and innovation
- IPCA + 3.40% to 4.89% per year
- Stand-alone working capital
- IPCA + 5.67% to 12.50% per year
Assumptions — Fixed portion of the TLP — November 2026: 7.72% per year · Regional Imbalance Coefficient: 0.64 (Northeast) · Programme factor: 0.8 to 2.3, depending on purpose and size · Location factor: 0.9 in priority municipalities; 1.1 elsewhere · Timely payment bonus: 0.85 applied to the real component · Inflation: actual IPCA for the period, in the floating-rate option · Implied inflation in the fixed-rate option: 5.50% per year (CMN Vote 57/2026) · Formula: fixed TLP × coefficient × programme factor × location factor × bonus.
Rates calculated in November 2026 under the methodology of CMN Resolution 5,013/2022. The minimum assumes a priority municipality and the timely payment bonus; the maximum, other municipalities without the bonus. The rate of each operation is the one in force in the month of signing, published by Banco do Nordeste.
History
Monthly rate history
Investment — medium-sized and large companies
IPCA + 3.78% to 9.78% per year
Down this month
Compared with October 2026, the minimum rate fell 0.20 percentage points and the maximum fell 0.51 percentage points. Since July 2026, the minimum rate fell 0.13 percentage points and the maximum fell 0.33 percentage points.
Maximum rateMinimum rate
November 2026: IPCA + 3.78% to 9.78% per year
Month-by-month values
| Month | Minimum | Maximum |
|---|---|---|
| November 2026 | IPCA + 3.78% | IPCA + 9.78% |
| October 2026 | IPCA + 3.98% | IPCA + 10.29% |
| September 2026 | IPCA + 4.06% | IPCA + 10.52% |
| August 2026 | IPCA + 4.02% | IPCA + 10.40% |
| July 2026 | IPCA + 3.91% | IPCA + 10.11% |
Series calculated with the fixed portion of the TLP for each month and the regional coefficient in force, under the methodology of CMN Resolution 5,013/2022. The range runs from a priority municipality with the timely payment bonus to a non-priority municipality without the bonus. The rate of each operation is the one published by Banco do Nordeste in the month of signing.
The fund
What it is and who can access it
Created by Law 7,827/1989, the FNE is managed by Banco do Nordeste under guidelines approved by the Deliberative Council of Sudene. The 2026 programme provides for BRL 52.57 billion, an increase of 11.1% over the previous year. For 2027, the estimate announced in September 2026 is BRL 60.9 billion, subject to approval by the Council.
The fund is open to private legal entities in the industrial, agro-industrial, tourism, commerce, services and infrastructure sectors, as well as consortia formed for the project. The determining criterion is the location of the project within the area covered by Sudene. The public sector is not eligible, with the exception of non-dependent state-owned companies in priority projects.
| Size | Annual gross revenue |
|---|---|
| Small-medium | Above BRL 4.8 million up to BRL 16 million |
| Medium I | Above BRL 16 million up to BRL 90 million |
| Medium II | Above BRL 90 million up to BRL 300 million |
| Large | Above BRL 300 million |
The size classification determines the programme factor, which is a component of the rate, and the limit on the fund’s participation in the investment.
Programmes
What is financed, tenors and grace periods
| Programme and purpose | Total tenor | Grace period |
|---|---|---|
| FNE Industrial — fixed and mixed investment | Up to 12 years | Up to 4 years |
| FNE Industrial — structuring and high-relevance projects | Up to 15 years | Up to 5 years |
| FNE Commerce and Services — fixed and mixed investment | Up to 12 years | Up to 4 years |
| Health services and the health industrial complex | Up to 20 years | Up to 5 years |
| FNE Proinfra — highways, railways, waterways and urban mobility | Up to 34 years | Up to 8 years |
| FNE Proinfra — power generation and transmission, ports and airports | Up to 24 years | Up to 8 years |
| FNE Proinfra — power distribution | Up to 20 years | Up to 8 years |
| FNE Verde — sanitation and infrastructure | Up to 34 years | Up to 8 years |
| FNE Verde — utility-scale renewable generation | Up to 24 years | Up to 8 years |
| FNE Verde — green hydrogen | Up to 20 years | Up to 5 years |
| FNE Innovation — fixed or mixed investment | Up to 15 years | Up to 5 years |
| FNE Proatur — accommodation | Up to 20 years | Up to 5 years |
| Stand-alone working capital | Up to 36 months | Up to 12 months |
Tenors from the FNE Programme 2026, including the grace period. In projects originating from public auctions, the tenor is limited to the term of the concession. Working capital associated with the investment may reach one third of the total financed. Financial charges, debt repayment, acquisition of land and buildings, with some exceptions, and imported goods with a domestic equivalent are not eligible.
Interest
How the rate is formed
Interest on non-rural operations of the constitutional funds follows the Constitutional Funds Interest Rate (TFC), set by CMN Resolution 5,013/2022. The rate combines inflation adjustment — the IPCA consumer price index in the floating-rate option, or implied inflation in the fixed-rate option — with a real component derived from the fixed portion of the TLP, BNDES’s long-term rate, set at signing and maintained until the end of the operation.
This real component is multiplied by four factors: the Regional Imbalance Coefficient (CDR), set at 0.64 for the Northeast; the programme factor, which varies with the size of the borrower and the purpose; the location factor, of 0.9 in priority municipalities and 1.1 elsewhere; and the timely payment bonus, of 0.85 for instalments paid by the due date.
The regional coefficient reduces the real component of the interest by more than one third in relation to the Centre-West, which explains the difference in cost between the funds. With the fixed portion of the TLP for November 2026, of 7.72% per year, the resulting real component for investment by medium-sized and large companies ranges from 3.78% to 9.78% per year, plus the variation in the IPCA, depending on size, location and timely payment.
| Purpose and size | Programme factor |
|---|---|
| Investment — revenue from BRL 4.8 million to BRL 90 million | 1.0 |
| Investment — revenue from BRL 90 million to BRL 300 million | 1.5 |
| Investment — revenue above BRL 300 million | 1.8 |
| Water, sewage and logistics infrastructure | 0.8 |
| Other infrastructure | 1.5 |
| Science, technology and innovation — above BRL 1 million | 0.9 |
| Stand-alone working capital — revenue above BRL 300 million | 2.3 |
Programme factors from the FNE Programme 2026. The timely payment bonus reduces the real component of the interest by 15%, not the total rate.
Limits and security
How much can be financed
The fund’s participation in the total investment varies with the size of the borrower and the classification of the municipality. For medium-sized companies, it ranges from 70% to 95%. For large companies, from 50% to 80%, with the higher percentages reserved for priority projects and for low-income and semi-arid municipalities. Projects aligned with the Ecological Transformation Plan and with the New Industry Brazil policy may reach 100%, except in power generation, transmission and distribution.
The limit per borrower is 1% of the fund’s net equity per company and 1.5% per economic group, rising to 3% in strategic projects. Accepted security includes personal or corporate guarantees, fiduciary assignment of movable and immovable assets, mortgages, pledges of machinery, receivables and accounts, and bank guarantees.
How Projecap works
From eligibility to signing
Eligibility assessment
Verification of the applicable programme, the borrower’s size, the classification of the municipality and the participation limit, with an estimate of the conditions.
Project and financial model
Preparation of the project in the format required by the bank, with the financial model, the sources and uses statement and the physical-financial schedule.
Security package
Definition of a security structure compatible with the project and with the bank’s credit policy.
Filing and information requests
Submission of the proposal, responses to requests from the technical and credit teams and follow-up through to approval.
Signing and disbursements
Support with formalisation, registration of security and evidence of milestones for the release of funds.
Frequently asked questions
Common questions
Can a large company use the FNE?
Yes. Companies with annual gross revenue above BRL 300 million are classified as large, with fund participation of between 50% and 80% of the investment, rising to 100% in projects aligned with the Ecological Transformation Plan and the New Industry Brazil policy.
Does the FNE finance working capital?
Yes. Working capital may be associated with the investment, up to one third of the total financed, or stand-alone, with a tenor of up to 36 months and ceilings defined by size and location.
What is the tenor for infrastructure concessions and PPPs?
Under FNE Proinfra, up to 34 years, with a grace period of up to 8, for highways, railways, waterways and urban mobility, and up to 24 years for generation, transmission, ports and airports. In projects originating from auctions, the tenor is limited to the term of the concession.
How does the timely payment bonus work?
When the instalment is paid by the due date, a factor of 0.85 is applied to the real component of the interest, equivalent to a 15% reduction in that component. In the event of late payment, the factor is 1.00.
Does the company need to be based in the Northeast?
The requirement is that the financed project be located in the area covered by Sudene, which comprises the nine states of the Northeast and municipalities in the north of Minas Gerais and Espírito Santo.
Can the FNE be combined with the Sudene tax incentives?
Yes. They are distinct and complementary instruments: the FNE finances the implementation of the project, and the incentive reduces corporate income tax on operating profit once the project is in operation.
Related
Other instruments of interest
BNDES
Finem, Automático, Finame and the Climate Fund: direct and indirect support for investment projects, with tenors of up to 34 years for infrastructure.
View detailsCapital marketsTax-incentivised and infrastructure debentures
Issuances under Laws 12,431/2011 and 14,801/2024 for priority projects: requirements, eligibility and steps of the offering.
View detailsContact
Talk to us about your project
The initial eligibility assessment is based on the basic information about the project. You can reach us through our direct channels or the contact form.
Sources and updates
- FNE Programme 2026 — Ministry of Integration and Regional Development (in Portuguese)
- CMN Vote 57/2026 — parameters from July 2026 (in Portuguese)
- Agência Gov — FNE budget for 2026 (in Portuguese)
Content updated in November 2026. Rates, limits and terms are set by the lenders and the competent authorities and may change; the conditions applicable to each transaction depend on the analysis of the project.